Jump to content

User:Illspirit/sandbox

From Wikipedia, the free encyclopedia
MV Glen Sannox and Hull 802 under construction at Ferguson Marine Engineering.

The ferry fiasco refers to an ongoing Scottish political controversy relating to the construction of two ferries, MV Glen Sannox and Hull 802, by Ferguson Marine Ltd, for the state-owned ferry operator Caledonian MacBrayne under direction of Caledonian Maritime Assets Ltd (CMAL), Transport Scotland, and the Scottish Government. The project has suffered from major delays and cost overruns. The main contractor, Ferguson Marine, was nationalised by the Scottish Government in December 2019 with debts of £70 million.[1][2] It is now classified as an executive non-departmental public body of the Scottish Government.[3]

Caledonian MacBrayne (CalMac) have an effective monopoly over ferry services to Scotland's numerous islands,[4] which are homes to approximately 45,000 people. They provide "lifeline services" to 22 of the bigger islands and on average its 34 vessels complete 466 crossings a day.[4] Delays and cancellations in recent years have been blamed by CalMac on aging ferries, with the average age of their ferries being 24 years. Of the 10 largest ferries, four are over 30 years old, which is beyond their expected operational life and Isle of Arran is 38 years old.[5] Research shows the replacement of ferries fell from one every 14 months from 1993 to 2007 (with 33,350 tonnes launched), to one every 36.1 months from 2007 to 2021 (with 16,188 tonnes launched).[6]

Procurement process[edit]

First Minister Nicola Sturgeon and Jim McColl at the Ferguson Marine shipyard on 31 August 2015

The last shipyard on the lower River Clyde, Ferguson Marine Ltd, went into administration in 2014.[7] In August of that year, then First Minister of Scotland Alex Salmond brokered a deal with industrialist Jim McColl to buy the business. A year later the business was awarded a £97 million contract to build two ferries to serve the Isle of Arran, replacing MV Isle of Arran, and the second to sail between Skye, North Uist and Harris. Inverclyde SNP MP Ronnie Cowan described this decision as "just reward" for the investment McColl had made in Ferguson Marine.[8] Ferguson Marine was announced as the preferred bidder on 31 August 2015 to coincide with an announcement from the UK Government about a £500 million expansion of the Royal Navy's nuclear submarine base at nearby Faslane.[9]

At the time there were concerns that Ferguson Marine had not built any ferries of this size in the recent past.[10] A new management team had recently been installed, and they too had no experience of building a ferry of this size.[10] The finances of Ferguson Marine were so tight that they told the Scottish Government they could not provide the financial guarantees that were stipulated in the contract.[10] These guarantees would make the shipbuilder responsible for any cost overruns. Of the six shipyards that tendered to build the ferries, Ferguson Marine put forward the most expensive bid, at £37 million more than the cheapest.[11]

As contract negotiations between CMAL and Ferguson Marine were concluding in September 2015, the chairman of CMAL, Erik Ostergard criticised the process, ongoing costs and the lack of Ferguson Marine's track record in projects of this nature. Ostergard was granted a letter from Scottish Ministers absolving his organisation of blame should the deal go bad.[10] CMAL's preference was to restart the procurement process. On 9th October Transport Scotland informed CMAL that after due consideration Scottish ministers were aware of the risks but content to proceed to award the contract.[12]

The contract was formally awarded to Ferguson Marine at the Scottish National Party Conference in Aberdeen on 16 October 2015. The announcement was made by Derek Mackay who was then a junior minister responsible for Transport and Islands.[8]

In September 2022, the BBC obtained documents indicating that Ferguson Marine received preferential treatment in the procurement process. CMAL held an in-person meeting with Ferguson, which was not extended to other bidders. Ferguson also uniquely received a 424-page document from a design consultant setting out CalMac's technical requirements, which was not extended to other bidders, who had to rely on a more limited 125-page specification. A key section of Ferguson's bid was largely copied from this longer document. Ferguson was also allowed to significantly change its design halfway through the tender by developing a variant mentioned but discounted in its original submission. This change allowed it to reduce its price by nearly £10 million.[13]

Design and build[edit]

The ferries would be a new design and use both marine diesel and liquified natural gas, which would allow the ferries to have lower emissions and allow operators flexibility over fuel sourcing and fuel costs. Another requirement was that the ferries would need larger bow thrusters and a stern thruster to make them more manoeuvrable in dock. Liquefied natural gas needs to be stored at -162 °C and the required tanks and bow thrusters meant each ferry being 200 tonnes heavier than an equivalent vessel.[14]

Within two months of the contract being awarded CMAL alerted problems at Ferguson Marine to the Project Steering Group (PSG). [12] The PSG was chaired by Transport Scotland and also included representatives from CMAL and CalMac and provided oversight of the project.[12] CMAL reported that Ferguson Marine failed to provide a detailed plan for building the ferries, failed to assign the correct workforce resources, quality issues were becoming apparent, and that there was lack of space at the shipyard.[12] CMAL could not intervene with the shipbuilder's handling of the project and could not prevent them from starting construction of the vessels before designs were finalised. During this time Transport Scotland only provided verbal updates on the project to Scottish Ministers.[12]

The contract stipulated that Ferguson Marine had to submit individual sets of drawings at least 30 days prior to work starting, as CMAL need approval from Lloyds Register.[12] Ferguson Marine reported that the requirement for CMAL to sign off every drawing slowed progress down and it could take several months for the shipbuilder to process CMAL's comments on the individual drawings.[12] The shipbuilder reported that it had to engage in out-of-sequence working to try to keep the project moving so it prioritised constructing the vessels to meet the milestone dates. Despite not having an approved design steel was cut on the on 15 December 2015 in line with the contractual date.[12] CMAL's onsite team identified problems during construction and issued reports to Ferguson Marine's management outlining their concerns and recommendations. The shipbuilder considered some of recommendations unnecessary and adding to costs and delays.[12] CMAL could not direct the builder to respond and by the time they went into administration only 52 per cent of the issues had been resolved.[12] From 2016 Ferguson Marine experienced cash flow problems which it blamed on problems with the contract. The Scottish Government approved a series of financial support and loans.[12] Audit Scotland subsequently found that although this financial support allowed the shipbuilder to retain its workforce, it did little to impact on the progress of the vessels.[12]

The delays got worse as the project progressed and by the time Glen Sannox was launched in November 2017 by First Minister Nicola Sturgeon,[15] and supposed to be in service by mid-2018, the launch itself was 431 days behind the contract's schedule and the ferry is not yet in service.[12] At launch windows had been painted on, the bulbous bow was made from flat sheet steel and the funnel not operational. These had been fitted so that the builder could claim a "milestone payment" from the Scottish Government.[10] There were 15 milestone payments which would culminate in the final payment of £97 million on delivery of the ferries. Three months before launch, the bulbous bow was rejected by an inspector from Lloyd's Register, and would need to be "renewed in entirety".[10]

Shortly before Ferguson Marine went into administration in August 2019, CMAL reported to the Project Steering Group that the vessels were showing signs of deterioration and that no more than six people were working on Glen Sannox and no more than two people working on vessel 802 an any one time.[12] The construction of both hulls continued to be marked by repeated delays and mechanical issues after nationalisation and a turnaround director, Tim Hair, was appointed between August 2019 and July 2021 who brought in improvements to the yard and created 100 jobs. However there was criticism of the £1,263,564 paid in fees to secure his services.[16]

Covid-19 further hampered construction, which was stopped for 11 weeks and initially opened with less than 10% of its workforce, who had to work with social distancing measures.[12] It emerged that the Scottish Government had paid a further £49 million from Covid Support Funds to Ferguson Marine.[17]

In February 2022, at least 400 electrical cables installed aboard Glen Sannox were found to be too short to reach equipment.[18] By the end of September 2022, only 26% of cables had been replaced. CMAL warned; "The current rate at which cable is pulled presents a serious threat to the project".[19] In November 2022, Ferguson Marine announced the ferries would rely on diesel alone for an unquantified period as they will need to be fitted with bespoke vacuum sensors to comply with rules for taking on refrigerated LNG, and that there was a lead-term of 36 weeks for delivery.[20]

The engines bought for the vessels had sat idle for six years, and Dr Spyros Hirdaris, a professor of maritime safety from Helsinki where the engine manufacturer Wartsila is based, stated that there was a "high possibility that the ferry engines won't work".[21]

Ongoing issues[edit]

Jim McColl claimed the contract was rushed through to coincide with the SNP conference in 2015 and the subsequent nationalisation of the yard was also rushed for political purposes. Nicola Sturgeon replied to McColl by saying that it was to save 400 jobs; McColl accused her of dishonesty as the number of people employed at the yard was actually closer to 150.[22]

In the meantime island community groups said the continued disruption and unreliability of ferry services have an "appalling" impact on them, and they are now in a "critical situation".[23] In the year to March 2021, Caledonian MacBrayne had been hit with fines of £3.2 million by Transport Scotland for delays. This figure exceeded state-owned ferry operator’s profits by £200,000.[24] In August 2022, police were called to deal with ferry customers who became “aggressive” at separate incidents in Mallaig and Ardrossan after service disruption following ferry breakdowns.[25]

The first vessel, now named Glen Sannox, is expected to be delivered five years behind schedule between March and May 2023.[26] Its unnamed sister ship, Hull 802, was expected to be delivered between October and December 2023, however further delays meant that as of September 2022 the ship is not expected to be delivered until the first quarter of 2024.[27][28] Both ships are also unlikely to operate their designated routes while the £130 million project to convert existing infrastructure in the ports to handle the new ferries remains incomplete. As of September 2022, the £40 million upgrade of Ardrossan's port, from which Glen Sannox will operate, was yet to start due to complexities on how the bill will be split between Transport Scotland, the port's owner, and North Ayrshire council, delaying the ferry operating on its planned route by a further three years.[29]

Inquiries[edit]

The Scottish Parliament’s Rural Economy and Connectivity Committee published a report in December 2020 after a 12 month inquiry.[30] The report branded the situation a “catastrophic failure” of management.[31] Further inquiries are being made by the parliament’s Audit Committee and following a public petition, by the Net Zero, Energy and Transport Committee.[32]

A report by Audit Scotland in March 2022 found the total cost to have risen to £240 million.[33] Audit Scotland also found "insufficient evidence to explain why Scottish Ministers made [the] decision" to award the contract to Ferguson Marine. The Auditor General, Stephen Boyle, described his "frustration" at not being able to review all the documentation relating to the awarding of the contract for the two ferries.[34] [35] Former SNP Deputy Leader Jim Sillars accused the Scottish Government of criminal "misconduct in public office" and lodged a complaint to Police Scotland requesting they investigate the missing documents. [36] This call was later supported by the Scottish Conservatives transport minister Graham Simpson[37] and SNP-led North Ayrshire Council, but Police Scotland confirmed they were not investigating the allegations.[38]

Just before a Parliamentary debate on the contract, Jenny Gilruth, Scotland's junior transport minister, produced an email to show that the contract was ultimately approved by Derek Mackay, a disgraced previous junior transport minister who left the government in February 2020.[39] [40] The same email trail showed that the final decision was escalated to John Swinney, the Deputy First Minister and Cabinet Finance Secretary, before the contract was finally awarded. Civil servants waited until he could be briefed before awarding the contract so he could check there were “no banana skins”.[41] He confirmed that the contract should proceed. Swinney subsequently claimed he was only providing "budget approval", rather than approval for the contract itself, as there would be “significant inefficiency” in Government if a senior Cabinet Minister was involved in approving every contract.[42][43] Keith Brown, the then Cabinet Secretary for the Economy, signed the contract on behalf of the Scottish Government, but he also denied responsibility claiming to sign in lieu of Mackay who was on holiday at the time.[44]

In a written response to the Public Audit Committee, Mackay said that he had "confidence" in the recommendation, and that there was expectation the contract would receive "sufficient monitoring and oversight". Scottish Conservatives transport spokesman Graham Simpson called for a public inquiry into the fiasco.[45] Nicola Sturgeon told the Scottish Parliament, the "buck stops with me", claiming "lessons will be learned". She promised a full review but stopped short of a public inquiry.[46]

In September 2022, Transport Scotland published a report by consultants Ernst and Young called “Project Neptune” which concluded that having multiple state agencies involved in the procurement process led to confusion over roles and responsibilities. The report suggested introducing a possible “Ferries Commissioner”, but added this could cause further confusion with “another stakeholder in an already crowded sector”.[47]

Following the BBC's disclosure of documents suggesting that Ferguson Marine had benefited from preferential treatment in the procurement process, John Swinney told the Scottish Parliament on 27 September 2022 that Audit Scotland would again investigate the issue.[13]

By the end of September 2022, the cost estimates from Ferguson Marine to put both ferries into service had risen by another £100 million to a total of £340 million. John Swinney stated that “no decision” would be made to release more public money towards the cost of completing the ferries until "due diligence" was carried out by the Scottish Government on the company, supported by external, independent financial advisors.[48] It was announced that Nicola Sturgeon would give evidence to the Public Audit Committee in November 2022.[49] There, she "completely and utterly" refuted there was anything untoward in the procurement process, but that there were powerful arguments in favour of Ferguson Marine given it was the last shipbuilder on the lower Clyde and thousands of jobs were at stake.[50]

In late November 2022, Audit Scotland announced that it was unable to account for £128.25 million in public money spent by Ferguson Marine on the ferries. Furthermore, it was unable to trace how a £30 million Scottish Government loan to Ferguson was spent.[51]

References[edit]

  1. ^ "Ferguson's went bust with debts of more than £70 million - with £50m owed to taxpayers". Greenock Telegraph. 27 September 2019.
  2. ^ "SNP ministers nationalise Clyde shipyard". The Herald. 16 August 2016.
  3. ^ "National public bodies directory - Executive non-departmental public bodies". Scottish Government. 26 July 2022. Retrieved 25 August 2022.
  4. ^ a b "IN DEPTH Scotland's ongoing ferry fiasco: what you need to know". The Week. 13 May 2022.
  5. ^ "The problem with CalMac's ageing ferries". The BBC. 13 May 2022.
  6. ^ "Ferry figures show the Scottish government is sailing in troubled water". The Times. 14 April 2021.
  7. ^ "Scotland's last commercial shipyard Ferguson Shipbuilders set to close". The Guardian. 15 August 2014. Retrieved 15 Aug 2014.
  8. ^ a b "Jim McColl's Ferguson shipyard wins £97m CalMac ferries deal". The National. 17 October 2015.
  9. ^ Ian, Jack (22 September 2022). "Chasing Steel". London Review of Books. 44 (18). Retrieved 22 September 2022.
  10. ^ a b c d e f "Scotland's ferry fiasco: What went wrong?". BBC Newsnight. Retrieved 22 June 2022.
  11. ^ "Ten things we learned about Scotland's ferry fiasco". BBC News. 27 September 2022. Retrieved 27 September 2022.
  12. ^ a b c d e f g h i j k l m n o "New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802". Audit Scotland. Retrieved 23 March 2022.
  13. ^ a b "Leaked dossier suggests Scottish ferry deal may have been rigged". BBC News. 27 September 2022. Retrieved 27 September 2022.
  14. ^ "Presentation to the Arran Ferry Committee 10 April 2017" (PDF). CMAL. Retrieved 27 June 2022.
  15. ^ "IN Pictures — Launch Of Ferry Glen Sannox At Port Glasgow". Inverclyde Now. 21 November 2017.
  16. ^ "Scotland's £2,783-a-day ferry fiasco 'fixer' got job after single phone interview". The Herald. Retrieved 7 November 2021.
  17. ^ "SNP paid £49m to build stricken Ferguson Marine ferries from Covid business support department". The Daily Express. 7 June 2022.
  18. ^ "Anger as short cables place new doubt over delivery of lifeline CalMac vessels". The Herald. 10 February 2022.
  19. ^ "Further threat ferry fiasco ships may never be delivered as cost to taxpayer soars by nearly £100m". The Herald. 29 September 2022.
  20. ^ Alf, Young. "Nicola Sturgeon faces boatload of questions on ferries fiasco". The Times. Retrieved 2 November 2022.
  21. ^ "Experts fear for delayed CalMac ferries' unused engines with risk of failure after years left idle". The Sunday Post. 3 April 2022.
  22. ^ "Jim McColl: Nicola Sturgeon accused of lying while tycoon admits own 'mistake'". The National. 3 May 2022.
  23. ^ "Island ferries chaos is 'critical', MSPs told". The Times. 29 June 2022.
  24. ^ "CalMac hit with £3.5 million performance-related fines". Ardrossan Herald. Retrieved 19 September 2022.
  25. ^ "Ferry bosses call in cops to deal with 'aggressive customers' as Scots routes disrupted". The Daily Record. 7 August 2022.
  26. ^ "Ferguson Marine ferries for CalMac delayed by another eight months to 2023". The Scotsman. 23 March 2022.
  27. ^ "Ferguson Marine says 802 ferry to be delayed again as chief predicts final cost of 'ferries fiasco'". The National. Retrieved 28 September 2022.
  28. ^ "Scottish ferries contract hit by fresh delay". BBC News. 28 September 2022.
  29. ^ "Islanders' anger over harbours unable to take delayed ferries". The Times. 5 September 2022.
  30. ^ "Inquiry into construction and procurement of ferry vessels in Scotland". The Scottish Parliament. 19 April 2021. Retrieved 28 August 2022.
  31. ^ "Damning Holyrood report brands CalMac ferry fiasco a 'catastrophic failure'". The Herald.
  32. ^ "Ship of state is veering wildly off course in bid to secure island links". The Times. 24 August 2022.
  33. ^ "Multiple failings have led to delays and cost overruns which continue to obstruct delivery of island ferries". Audit Scotland.
  34. ^ "Auditor General expresses 'frustration' at lack of documents on ferry scandal". The Insider. 21 April 2022.
  35. ^ "New Vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802". The Scottish Parliament. Retrieved 27 June 2022.
  36. ^ "Jim Sillars lodges police complaint over ministers' ferry fiasco 'missing documents'". The Herald. Retrieved 6 May 2022.
  37. ^ "New call for criminal probe over 'rigged' Scots ferry fiasco contract". The Herald. Retrieved 27 September 2022.
  38. ^ Martin, Williams. "Police not investigating Scots ferry fiasco despite complaints". The Herald Newspaper. Retrieved 11 November 2022.
  39. ^ Baynes, Chris (6 February 2020). "Scotland's finance secretary quits after allegedly sending hundreds of messages to 16-year-old boy". The Independent. Archived from the original on 6 February 2020. Retrieved 6 February 2020.
  40. ^ "Jenny Gilruth produces email that claims Derek Mackay approved ferry fiasco contract". The Herald. 11 May 2022.
  41. ^ "Revealed: John Swinney consulted before ferry fiasco contract was given to Jim McColl's Ferguson Marine". The Herald. Retrieved 11 May 2022.
  42. ^ "John Swinney - I only gave budget approval in ferry deal". BBC. 12 May 2022.
  43. ^ "John Swinney: Public inquiry into ferries scandal can be considered in 'due time'". The Telegraph. 16 May 2022.
  44. ^ "Derek Mackay on holiday when ferries deal signed puts new pressure on Sturgeon". The Herald. 26 March 2022.
  45. ^ "Ferries contract decision 'remains unexplained'". The Insider. 23 March 2022.
  46. ^ "Nicola Sturgeon: Buck stops with me over ferry contract row". BBC. 24 March 2023.
  47. ^ "Plans for sweeping changes to how ferries are run". BBC News. 8 September 2022.
  48. ^ "Cost to taxpayer of Scotland's ferry fiasco soars to nearly £340m". The Herald. 28 September 2022.
  49. ^ "Nicola Sturgeon to give evidence on ferry fiasco". Holyrood. 21 October 2022. Retrieved 21 October 2022.
  50. ^ "Nicola Sturgeon rejects cronyism accusation over ferries contract". The Guardian. 4 November 2022. Retrieved 4 November 2022.
  51. ^ "Anger as £130m of taxpayers' money 'lost' by Scot Gov-run shipyard". The Herald. 30 November 2022. Retrieved 30 November 2022.

External links[edit]