The 2010 U.S. population within {{convert|10|mi}} of Comanche Peak was 30,653, an increase of 44.1 percent in a decade, according to an analysis of U.S. Census data for msnbc.com. The 2010 U.S. population within {{convert|50|mi}} was 1,755,528, an increase of 22.9 percent since 2000. Cities within 50 miles include Fort Worth (41 miles to city center).<ref>[[Bill Dedman]], Nuclear neighbors: Population rises near US reactors, ''[[msnbc.com]]'', April 14, 2011 http://www.msnbc.msn.com/id/42555888/ns/us_news-life/ Accessed May 1, 2011.</ref> |
The 2010 U.S. population within {{convert|10|mi}} of Comanche Peak was 30,653, an increase of 44.1 percent in a decade, according to an analysis of U.S. Census data for msnbc.com. The 2010 U.S. population within {{convert|50|mi}} was 1,755,528, an increase of 22.9 percent since 2000. Cities within 50 miles include Fort Worth (41 miles to city center).<ref>[[Bill Dedman]], Nuclear neighbors: Population rises near US reactors, ''[[msnbc.com]]'', April 14, 2011 http://www.msnbc.msn.com/id/42555888/ns/us_news-life/ Accessed May 1, 2011.</ref> |
||
== Units 3 and 4 == |
|||
On September 19, 2008, Luminant filed an application with the NRC for a [[Combined Construction and Operating License]] (COL) for two new reactors.<ref> {{cite web |
|||
| url= http://www.nrc.gov/reactors/new-reactors/col/comanche-peak.html |
|||
| title= Comanche Peak Nuclear Power Plant, Units 3 and 4 Application |
|||
| date= 2008-09-19 |publisher= U.S. [[Nuclear Regulatory Commission]] (NRC) |
|||
| accessdate= 2008-09-19 }}</ref> The reactor design selected is the US version of the 1,700 [[MWe]] [[Advanced Pressurized Water Reactor]] (US-APWR), developed by [[Mitsubishi Heavy Industries]] (MHI). The project is a joint venture, with Luminant owning 88 percent and 12 percent owned by MHI.<ref> {{cite news |
|||
| url= http://www.bizjournals.com/dallas/stories/2008/09/15/daily72.html |
|||
| title= Luminant seeks permission to expand nuclear power plant |
|||
| date= 2008-09-19 | work= [[Dallas Business Journal]] | publisher= |
|||
| accessdate= 2008-09-19 }}</ref> |
|||
Luminant did not release an estimate of the project's cost, but CEO David Campbell said Luminant would try to build its new reactors at the low end of current industry estimates, which he said range from $2,500 to $6,000 a kilowatt — $8.5 billion to $20.4 billion for a 3,400 MW plant.<ref> {{cite news |
|||
| url= http://www.reuters.com/article/bondsNews/idUSN1952971720080919?sp=true |
|||
| title= Luminant seeks new reactor, 3rd Texas filing |
|||
| last= O'Grady | first= Eileen | date= 2008-09-19 | publisher= [[Reuters]] |
|||
| accessdate= 2008-09-19 }}</ref> |
|||
Some environmental and [[Anti-nuclear movement in the United States|anti-nuclear organizations]] and individuals oppose the plant expansion, citing environmental, public safety and cost concerns. These include the Sustainable Energy and Economic Development Coalition, [[Public Citizen]] and state Rep. [[Lon Burnam]].<ref>[http://www.star-telegram.com/business/story/1424379.html Hearing today involves opponents to new reactors at Comanche Peak]</ref> |
|||
== Reactor data == |
== Reactor data == |
Revision as of 07:17, 7 September 2011
Comanche Peak Nuclear Power Plant | |
---|---|
Country | United States |
Coordinates | 32°17′54″N 97°47′06″W / 32.2983°N 97.785°W |
Status | Operational |
Construction began | 1974-93 |
Commission date | Unit 1: April 17, 1990 Unit 2: April 6, 1993 |
Operator(s) | Luminant Generation Co. |
Power generation | |
Nameplate capacity |
|
External links | |
Website | www.luminant.com/plants/comanche_peak |
Commons | Related media on Commons |
Comanche Peak Nuclear Power Plant is located in Somervell County, Texas. The nuclear power plant is located 40 miles (65 km) southwest of Ft. Worth and about 60 miles (100 km) southwest of Dallas. It relies on nearby Squaw Creek Reservoir for cooling water. The plant has about 1,300 employees and is operated by Luminant Generation, a subsidiary of Energy Future Holdings Corporation.
Construction of the two Westinghouse pressurized water reactors began in 1974. Unit 1, originally rated at 1,084 MWe, came online on April 17, 1990. Its current, 40-year operating license is valid until February 8, 2030. Unit 2, 1,124 MWe, followed on April 6, 1993 and is licensed to operate until February 2, 2033 when it has to renew its license. As of 2006[update] Unit 2 was the second-last power reactor to come online in the USA, followed only by Watts Bar 1.
In June 2008, the U.S. Nuclear Regulatory Commission (NRC) approved a request to increase the generating capacity of units 1 and 2 by approximately 4.5% each. Luminant Generation Co. implemented the changes during refueling outages. Unit 1 was uprated in autumn 2008 with a capacity increase of approximately 1,210 to 1,259 MWe and Unit 2, the capacity of which rose from an estimated 1,208 to 1,245 MWe, was uprated in autumn 2009.[1]
Surrounding population
The Nuclear Regulatory Commission defines two emergency planning zones around nuclear power plants: a plume exposure pathway zone with a radius of 10 miles (16 km), concerned primarily with exposure to, and inhalation of, airborne radioactive contamination, and an ingestion pathway zone of about 50 miles (80 km), concerned primarily with ingestion of food and liquid contaminated by radioactivity.[2]
The 2010 U.S. population within 10 miles (16 km) of Comanche Peak was 30,653, an increase of 44.1 percent in a decade, according to an analysis of U.S. Census data for msnbc.com. The 2010 U.S. population within 50 miles (80 km) was 1,755,528, an increase of 22.9 percent since 2000. Cities within 50 miles include Fort Worth (41 miles to city center).[3]
Units 3 and 4
On September 19, 2008, Luminant filed an application with the NRC for a Combined Construction and Operating License (COL) for two new reactors.[4] The reactor design selected is the US version of the 1,700 MWe Advanced Pressurized Water Reactor (US-APWR), developed by Mitsubishi Heavy Industries (MHI). The project is a joint venture, with Luminant owning 88 percent and 12 percent owned by MHI.[5] Luminant did not release an estimate of the project's cost, but CEO David Campbell said Luminant would try to build its new reactors at the low end of current industry estimates, which he said range from $2,500 to $6,000 a kilowatt — $8.5 billion to $20.4 billion for a 3,400 MW plant.[6]
Some environmental and anti-nuclear organizations and individuals oppose the plant expansion, citing environmental, public safety and cost concerns. These include the Sustainable Energy and Economic Development Coalition, Public Citizen and state Rep. Lon Burnam.[7]
Reactor data
The Comanche Peak Nuclear Power Plant consist of two operational reactors, two additional units are planned.
Reactor unit[8] | Reactor type | Capacity | Construction started | Electricity grid connection | Commercial operation | Shutdown | |
---|---|---|---|---|---|---|---|
Net | Gross | ||||||
Comanche Peak-1 | Westinghouse 4-loop | 1209 MW | 1259 MW | 19.12.1974 | 24.04.1990 | 13.08.1990 | |
Comanche Peak-2 | Westinghouse 4-loop | 1158 MW | 1189 MW | 19.12.1974 | 09.04.1993 | 03.08.1993 | |
Comanche Peak-3 (planned)[9] | US-APWR | 1700 MW | MW | ||||
Comanche Peak-4 (planned)[10] | US-APWR | 1700 MW | MW |
References
- ^ "Comanche Peak to increase output". World Nuclear News. 2008-06-30. Retrieved 2008-09-19.
- ^ http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/emerg-plan-prep-nuc-power-bg.html
- ^ Bill Dedman, Nuclear neighbors: Population rises near US reactors, msnbc.com, April 14, 2011 http://www.msnbc.msn.com/id/42555888/ns/us_news-life/ Accessed May 1, 2011.
- ^ "Comanche Peak Nuclear Power Plant, Units 3 and 4 Application". U.S. Nuclear Regulatory Commission (NRC). 2008-09-19. Retrieved 2008-09-19.
- ^ "Luminant seeks permission to expand nuclear power plant". Dallas Business Journal. 2008-09-19. Retrieved 2008-09-19.
- ^ O'Grady, Eileen (2008-09-19). "Luminant seeks new reactor, 3rd Texas filing". Reuters. Retrieved 2008-09-19.
- ^ Hearing today involves opponents to new reactors at Comanche Peak
- ^ Power Reactor Information System of the IAEA: „United States of America: Nuclear Power Reactors- Alphabetic“
- ^ Power Reactor Information System of the IAEA: „Nuclear Power Reactor Details - COMANCHE PEAK-3“
- ^ Power Reactor Information System of the IAEA: „Nuclear Power Reactor Details - COMANCHE PEAK-4“
External links
- "Comanche Peak 1". NRC. 2008-02-14. Retrieved 2008-09-19.
- "Comanche Peak 2". NRC. 2008-02-14. Retrieved 2008-09-19.
- "Comanche Peak". U.S. Nuclear Plants. U.S. Energy Information Administration (EIA). Retrieved 2008-09-19.