The late 1960s and early 1970s saw a rapid growth in the development of [[nuclear power in the United States]]. By 1976, however, many nuclear plant proposals were no longer viable due to a slower rate of growth in electricity demand, significant cost and time overruns, and more complex regulatory requirements. Also, there was considerable [[Anti-nuclear movement in the United States|public opposition to nuclear power]] in the USA by this time, which contributed to delays in licensing planned nuclear power stations, and further increased costs.<ref>[http://books.google.com.au/books?id=CK48AAAAIAAJ&pg=PA16&lpg=PA16&dq=nuclear+power+decline+u.s.&source=bl&ots=ET122QK4zp&sig=iIvB6tzXxEvrZhwtioZZWMniMKQ&hl=en&ei=JfosSvflDMeAkQX43a3nCg&sa=X&oi=book_result&ct=result&resnum=4#PPA16,M1 Nuclear power: Futures, Costs, and Benefits] p. 16.</ref>
The late 1960s and early 1970s saw a rapid growth in the development of [[nuclear power in the United States]]. By 1976, however, many nuclear plant proposals were no longer viable due to a slower rate of growth in electricity demand, significant cost and time overruns, and more complex regulatory requirements. Also, there was considerable [[Anti-nuclear movement in the United States|public opposition to nuclear power]] in the USA by this time, which contributed to delays in licensing planned nuclear power stations, and further increased costs.<ref>[http://books.google.com.au/books?id=CK48AAAAIAAJ&pg=PA16&lpg=PA16&dq=nuclear+power+decline+u.s.&source=bl&ots=ET122QK4zp&sig=iIvB6tzXxEvrZhwtioZZWMniMKQ&hl=en&ei=JfosSvflDMeAkQX43a3nCg&sa=X&oi=book_result&ct=result&resnum=4#PPA16,M1 Nuclear power: Futures, Costs, and Benefits] p. 16.</ref>

Many license applications for proposed new reactors, filed with the [[Nuclear Regulatory Commission]] in the 2000s, have been suspended or cancelled.<ref name=eo>Eileen O'Grady. [http://uk.reuters.com/article/idUSTRE64N5S420100524 Entergy says nuclear remains costly] ''Reuters'', May 25, 2010.</ref><ref>Terry Ganey. [http://www.columbiatribune.com/news/2009/apr/23/amerenue-pulls-plug-callaway-2/ AmerenUE pulls plug on project] ''Columbia Daily Tribune'', April 23, 2009.</ref> The number of reactors with any serious prospect of being built as of the end of 2010 is about a dozen.<ref name=matt2010>Matthew L. Wald (December 7, 2010). [http://green.blogs.nytimes.com/2010/12/07/nuclear-renaissance-is-short-on-largess/ Nuclear ‘Renaissance’ Is Short on Largess] ''[[The New York Times]]''.</ref><ref>Nuclear power in America: Constellation's cancellation, (October 16, 2010), ''The Economist'', p. 61.</ref>


==Canceled nuclear plants and units==
==Canceled nuclear plants and units==

Revision as of 20:17, 22 June 2011

This is a list of canceled nuclear plants in the United States.

The late 1960s and early 1970s saw a rapid growth in the development of nuclear power in the United States. By 1976, however, many nuclear plant proposals were no longer viable due to a slower rate of growth in electricity demand, significant cost and time overruns, and more complex regulatory requirements. Also, there was considerable public opposition to nuclear power in the USA by this time, which contributed to delays in licensing planned nuclear power stations, and further increased costs.[1]

Many license applications for proposed new reactors, filed with the Nuclear Regulatory Commission in the 2000s, have been suspended or cancelled.[2][3] The number of reactors with any serious prospect of being built as of the end of 2010 is about a dozen.[4][5]

Canceled nuclear plants and units

Name [6] Unit Reactortype Status Net
capacity
in MW
Gross
capacity
in MW
Contract
year
Construct-
ion
started
Project
close
Allens Creek 1 Boiling water reactor Canceled Plan 1,160 1,207 1973 - 01.09.1982
Allens Creek 2 Boiling water reactor Canceled Plan 1,160 1,207 1973 - 01.09.1976
Atlantic 1 Pressurized water reactor Canceled Plan 1,150 1,212 1972 - 01.12.1978
Atlantic 2 Pressurized water reactor Canceled Plan 1,150 1,212 1972 - 01.12.1978
Bailly 1 Boiling Water Reactor Canceled Plan 660 686 1967 01.01.1974 01.08.1981
Barton 1 Boiling water reactor Canceled Plan 1,209 1,254 1972 - 01.11.1977
Barton 2 Boiling water reactor Canceled Plan 1,209 1,254 1972 - 01.11.1977
Barton 3 Boiling water reactor Canceled Plan 1,209 1,254 1974 - 01.11.1975
Barton 4 Boiling water reactor Canceled Plan 1,209 1,254 1974 - 01.11.1975
Bellefonte 1 Pressurized water reactor Canceled Construction 1,235 1,263 1970 01.09.1974 01.01.1988
Bellefonte 2 Pressurized water reactor Canceled Construction 1,235 1,263 1970 01.09.1974 01.01.1988
Black Fox 1 Boiling water reactor Canceled Construction 1,150 1,226 1973 01.07.1978 01.02.1982
Black Fox 2 Boiling water reactor Canceled Construction 1,150 1,226 1973 01.07.1978 01.02.1982
Blue Hills 1 Pressurized water reactor Canceled Plan 930 957 1973 - 01.08.1978
Blue Hills 2 Pressurized water reactor Cancelled Plan 930 957 1974 - 01.08.1978
Bodega Bay
Callaway 2 Pressurized water reactor Canceled Construction 1,120 1,176 1973 01.10.1975 01.10.1981
Cherokee 1 Pressurized water reactor Canceled Construction 1,280 1,343 1973 01.06.1976 01.04.1983
Cherokee 2 Pressurized water reactor Canceled Construction 1,280 1,343 1973 01.06.1976 01.11.1982
Cherokee 3 Pressurized water reactor Canceled Construction 1,280 1,343 1973 01.06.1976 01.11.1982
Clinch River - Fast breeder Canceled Plan 350 380 1973 - 01.11.1983
Clinton 2 Boiling water reactor Canceled Construction 933 985 1973 01.10.1975 01.10.1983
Davis Besse 2 Pressurized water reactor Canceled Plan 910 960 1973 - 01.01.1980
Davis Besse 3 Pressurized water reactor Canceled Plan 910 960 1973 - 01.01.1980
Douglas Point (US) 1 Boiling water reactor Canceled Plan 1,178 1,206 1972 - 01.05.1980
Douglas Point (US) 2 Boiling water reactor Canceled Plan 1,178 1,206 1972 - 01.01.1978
Erie 1 Pressurized water reactor Canceled Plan 1,260 1,300 1976 - 01.01.1980
Erie 2 Pressurized water reactor Canceled Plan 1,260 1,300 1976 - 01.01.1980
Floating 1 Pressurized water reactor Canceled Plan 1,150 1,211 - - 01.01.1979
Fort Calhoun 2 Pressurized water reactor Canceled Plan 1,136 1,182 1972 - 01.02.1977
Fulton 1 HTGR Canceled Plan 1,160 1,200 - - 01.03.1976
Fulton 2 HTGR Canceled Plan 1,160 1,200 - - 01.03.1976
Greene County - Pressurized water reactor Canceled Plan 1,191 1,277 - - 01.04.1979
Greenwood 2 Pressurized water reactor Canceled Plan 1,208 1,268 - - 01.03.1980
Greenwood 3 Pressurized water reactor Canceled Plan 1,208 1,268 - - 01.03.1980
Columbia (WPPSS-1) 1 Pressurized water reactor Canceled Construction 1,259 1,339 1972 01.08.1975 01.01.1983
Columbia (WPPSS-4) 4 Pressurized water reactor Canceled Construction 1,250 1,340 1974 01.08.1975 01.01.1982
Hartsville A1 Boiling water reactor Canceled Construction 1,233 1,269 1972 01.04.1976 01.08.1984
Hartsville A2 Boiling water reactor Canceled Construction 1,233 1,269 1972 01.04.1976 01.08.1984
Hartsville B1 Boiling water reactor Canceled Construction 1,233 1,269 - 01.04.1976 01.08.1982
Hartsville B2 Boiling water reactor Canceled Construction 1,233 1,269 - 01.04.1976 01.08.1982
Haven 1 Pressurized water reactor Canceled Plan 900 960 - - 01.02.1980
Haven 2 Pressurized water reactor Canceled Plan 900 960 - - 01.05.1978
Hope Creek 2 Boiling water reactor Canceled Construction 1,067 1,118 1969 01.03.1976 01.12.1981
Jamesport 1 Pressurized water reactor Canceled Plan 1,150 1,182 - - 01.01.1980
Jamesport 2 Pressurized water reactor Canceled Plan 1,150 1,182 - - 01.01.1980
Marble Hill 1 Pressurized water reactor Canceled Construction 1,030 1,090 - 01.07.1977 01.01.1984
Marble Hill 2 Pressurized water reactor Canceled Construction 1,130 1,190 - 01.07.1977 01.01.1984
Midland 1 Pressurized water reactor Canceled Construction 491 526 1968 01.03.1973 01.07.1986
Midland 2 Pressurized water reactor Canceled Construction 816 855 1968 01.03.1973 01.07.1986
Montague 1 Boiling water reactor Canceled Plant 1,150 1,298 - - 01.12.1980
Montague 2 Boiling water reactor Canceled Plan 1,150 1,298 - - 01.12.1980
Nep 1 Pressurized water reactor Canceled Plan 1,150 1,194 - - 01.01.1980
Nep 2 Pressurized water reactor Canceled Plan 1,150 1,194 - - 01.01.1980
North Coast (formerly Aguirre) 1 Pressurized water reactor Canceled Plan 583 614 - - 01.12.1978
North Anna 3 Pressurized water reactor Canceled Construction 907 950 1971 01.06.1971 01.11.1982
North Anna 4 Pressurized water reactor Canceled Construction 907 950 1971 01.12.1971 01.11.1980
Pebble Springs 1 Pressurized water reactor Canceled Plan 1,260 1,314 - - 01.09.1982
Pebble Springs 2 Pressurized water reactor Canceled plan 1,260 1,314 - - 01.09.1982
Perkins 1 Pressurized water reactor Canceled Plan 1,287 1,345 - - 01.02.1982
Perkins 2 Pressurized water reactor Canceled Plan 1,287 1,345 - - 01.02.1982
Perkins 3 Pressurized water reactor Canceled Plan 1,287 1,345 - - 01.02.1982
Perry 2 Boiling water reactor Canceled Construction 1,205 - - 01.10.1974 01.04.1984
Phipps Bend 1 Boiling water reactor Canceled Construction 1,233 1,269 - 01.10.1977 01.08.1982
Phipps Bend 2 Boiling water reactor Canceled Construction 1,233 1,269 - 01.10.1977 01.08.1982
Pilgrim 2 Pressurized water reactor Canceled Plan 1,180 1,240 - - 01.09.1981
River Bend 2 Pressurized water reactor Canceled Construction 934 991 1972 01.08.1975 01.01.1984
Satsop (WPPSS-3) 3 Pressurized water reactor Canceled Construction 1,240 1,324 1973 01.04.1977 01.01.1983
Satsop (WPPSS-5) 5 Pressurized water reactor Canceled Construction 1,240 1,316 1974 01.04.1977 01.01.1982
Seabrook 2 Pressurized water reactor Cancelled Construction 1,149 1,199 1972 01.07.1976 01.01.1988
Sears Isle
Shearon Harris 2 Pressurized water reactor Canceled Construction 900 960 1971 01.01.1978 01.12.1983
Shearon Harris 3 Pressurized water reactor Canceled Construction 900 960 1971 01.01.1978 01.12.1983
Shearon Harris 4 Pressurized water reactor Canceled Construction 900 960 1971 01.01.1978 01.12.1983
Skagit 1 Boiling water reactor Canceled Plan 1,275 1,335 - - 01.08.1983
Skagit 2 Boiling water reactor Cancelled Plan 1,275 1,335 - - 01.08.1983
Somerset 1
Somerset 2
South River 1
South River 2
South River 3
Stanislaus 1
Stanislaus 2
Sterling 1 Pressurized water reactor Canceled Plan 1,150 1,185 - - 01.01.1980
Sundesert 1
Sundesert 2
Surry 3 Pressurized water reactor Canceled Construction 859 919 1972 01.01.1974 01.03.1977
Surry 4 Pressurized water reactor Canceled Construction 859 919 1972 01.01.1974 01.03.1977
Tyrone 1 Pressurized water reactor Canceled Plan 1,150 1,188 - - 01.07.1979
Yellow Creek 1 Pressurized water reactor Canceled Construction 1,285 1,339 1974 01.02.1978 01.02.1978
Yellow Creek 2 Pressurized water reactor Canceled Construction 1,285 1,339 1974 01.02.1978 01.02.1978
Zimmer 1 Boiling water reactor Canceled Construction 810 840 - 01.10.1972 01.01.1984